Cell manufacturing/EOL Testing
From KIproBatt Wiki
< Battery value chain | Process | Cell manufacturingBattery value chain/Process/Cell manufacturing/EOL Testing
(Created page with "{{Semantic Element |label=Cell manufacturing/EOL Testing |description===Production process== *Before the cells leave the factory, they are tested in an EOL test rig. *The...") |
Simon Stier (talk | contribs) (updated from EOL_Testing) Tag: 2017 source edit |
||
Line 1: | Line 1: | ||
− | {{Semantic Element | + | {{GlossaryEntry}}{{Semantic Element |
|label=Cell manufacturing/EOL Testing | |label=Cell manufacturing/EOL Testing | ||
− | |description===Production process== | + | |description= |
+ | ===Production process=== | ||
− | * | + | *After finalizing the cell production, cells are tested in an End-Of-Line (EOL) testing process |
− | * | + | *Cells are transferred from their aging storage location to the testing station |
− | * | + | *EOL testing process may include the following tests: |
− | * | + | **Capacity measurements (i.e., discharge to state of charge (SOC) of transport), |
− | * | + | **Pulse tests, |
− | * | + | **Internal resistance measurements (DC), |
− | + | **Optical inspections, | |
+ | **OCV tests, | ||
+ | **Leakage tests, | ||
+ | **... | ||
+ | *Sorting of cells according to EOL results (i.e., performance grading) | ||
+ | *Packaging and transportation to customer | ||
− | |||
− | * | + | ===Process parameters & requirements=== |
+ | |||
+ | *SOC for transportation: 5 % - 20 % SOC | ||
*Permissible loss rate: < 5 mV per week | *Permissible loss rate: < 5 mV per week | ||
*Increased loss rate: > 5mV per week may indicate e.g. cell-internal short circuits | *Increased loss rate: > 5mV per week may indicate e.g. cell-internal short circuits | ||
− | ==Technology alternatives== | + | ===Technology alternatives=== |
− | *Different test sequences and durations | + | *Different test sequences and durations |
− | ==Quality influences== | + | ===Quality influences=== |
*Cell handling | *Cell handling | ||
− | ==Quality characteristics== | + | ===Quality characteristics=== |
*Low self-discharge | *Low self-discharge | ||
Line 31: | Line 38: | ||
*Constant capacity | *Constant capacity | ||
− | ==Source== | + | ===Source=== |
Heimes, H.H.; Kampker, A.; Lienemann, C.; Locke, M.; Offermanns, C.; Michaelis, S.; Rahimzei, E. (2018) ''Lithium-Ion Battery Cell Production Process''; PEM of RWTH Aachen and VDMA, 3rd Edition, ISBN:978-3-947920-03-7 | Heimes, H.H.; Kampker, A.; Lienemann, C.; Locke, M.; Offermanns, C.; Michaelis, S.; Rahimzei, E. (2018) ''Lithium-Ion Battery Cell Production Process''; PEM of RWTH Aachen and VDMA, 3rd Edition, ISBN:978-3-947920-03-7 | ||
+ | |||
|relations={{Semantic Link | |relations={{Semantic Link | ||
|property=Has predecessor | |property=Has predecessor |
Revision as of 16:21, 19 November 2021
Description
Production process
- After finalizing the cell production, cells are tested in an End-Of-Line (EOL) testing process
- Cells are transferred from their aging storage location to the testing station
- EOL testing process may include the following tests:
- Capacity measurements (i.e., discharge to state of charge (SOC) of transport),
- Pulse tests,
- Internal resistance measurements (DC),
- Optical inspections,
- OCV tests,
- Leakage tests,
- ...
- Sorting of cells according to EOL results (i.e., performance grading)
- Packaging and transportation to customer
Process parameters & requirements
- SOC for transportation: 5 % - 20 % SOC
- Permissible loss rate: < 5 mV per week
- Increased loss rate: > 5mV per week may indicate e.g. cell-internal short circuits
Technology alternatives
- Different test sequences and durations
Quality influences
- Cell handling
Quality characteristics
- Low self-discharge
- Low internal resistance
- Constant capacity
Source
Heimes, H.H.; Kampker, A.; Lienemann, C.; Locke, M.; Offermanns, C.; Michaelis, S.; Rahimzei, E. (2018) Lithium-Ion Battery Cell Production Process; PEM of RWTH Aachen and VDMA, 3rd Edition, ISBN:978-3-947920-03-7
Semantic Links
Add or edit outgoing links
To edit incoming links, go to the subjects site.
Outgoing
Subject | Property | Object |
---|---|---|
Cell manufacturing/EOL Testing | HasPredecessor | Cell manufacturing/Aging |
Cell manufacturing/EOL Testing | HasSuccessor | Module manufacturing |